Latent defects and appropriate remedial solutions

    Latent defects and appropriate remedial solutions

    News

    David Weare is a partner and Ian Smith is a senior associate at Fladgate LLP

    The recent decision in St James’s Oncology SPC Ltd v Lendlease Construction provides helpful guidance to PFI-project companies, design and build contractors, and employers generally when dealing with latent-defect claims.

    The case concerned a new oncology centre at Leeds Hospital, designed, built and operated by St James’s Oncology SPC Ltd (the claimant) pursuant to a project agreement under the government’s private finance initiative.

    The claimant engaged Lendlease Construction as its design and build subcontractor for the works.

    “A building regulations completion certificate is not conclusive evidence that the regulations have been complied with”

    The claimant was responsible for procuring that the project operations were at all times performed, “except to the extent expressly stated to the contrary in the trust’s construction requirements or the service-level specifications, in compliance with all applicable NHS requirements”. This included health technical memoranda (HTMs).

    Proceedings were commenced against Lendlease three days before expiry of the 12-year limitation period. The claimant alleged that when the oncology centre was built, there were serious fire-safety and electrical engineering defects.

    The judge noted “It is common ground that […] where HTMs provide guidance, they are not always applicable to every design solution, and it is possible to agree derogations from that guidance”. 

    The design and build subcontract specifically addressed the permissibility of alternative engineering approaches provided they achieved a standard of safety equal to or better than the relevant HTM. 

    As at the date of trial, no remedial work had been undertaken by the claimant. Lendlease alleged that, as the claimant did not intend to implement any remedial work, it was not entitled to damages.

    Lendlease also argued that any aspects of the design that were not compliant with the technical specifications had been approved by all relevant parties.

    The judge found against Lendlease on almost every point.

    What it means 

    Several key issues and observations arise out of this judgment of which those engaged in PFI projects and construction projects generally should be aware.

    First, all specifications and other guidance notes must be reviewed separately to see whether they need to be followed to the letter. In this case, the contract did allow a fire-engineering approach that deviates from the specification, provided it would achieve a standard equal to or better than the contract requirements.

    Additionally, the issue of a building regulations completion certificate is not conclusive evidence that the regulations have been complied with, and a design-review procedure does not necessarily relieve a defendant of its design obligation, regardless of whether the revised design is accepted or not. 

    Readers should also be aware that a holistic design that allows for areas of non-compliance on the basis that the overall design is safe is unlikely to be a good defence. 

    Furthermore, when considering the measure of damages in defective work cases and the relevance of intention to reinstate, the general rule is that the measure of damages will be the cost of making good unless that cost is disproportionate. Damages for the cost of cure will be awarded provided that the claimant is “seeking compensation for a genuine loss and not merely using a technical breach to secure an uncovenanted profit”. It is also important to note that the court is not concerned with how the claimant will use any damages that may be awarded, provided that the loss can be established. However, in cases of defective work, the intention of the claimant to carry out remedial work is relevant insofar as it goes to the reasonableness of reinstatement and the extent of the loss sustained.

    Remedial work

    A claimant may delay carrying out remedial work until damages representing the cost of the proposed remediation are awarded by the court. The cost of proposed remedial work may fairly and properly be assessed as at the date of the trial and not when the defects were or ought to have been known and remediated. A claimant is also entitled to make an allowance for inflation to cover price increases from the award of damages to letting a remedial works contract, and the correct measure of loss is the cost of reinstatement.

    When deciding between rival remedial schemes, if two remedial schemes are proposed to rectify a defect and one is implemented on expert advice, the defendant is liable for the costs of that scheme unless it could be said that the expert advice is unreasonable, and finally, it is not an answer to a claimed remedial scheme to demonstrate that the defects could have been rectified through an alternative scheme at a lower cost.

    The St James’s Oncology ruling is timely guidance for those engaged in PFI projects and construction projects generally, not least because it highlights a number of observations that parties should be aware of in relation to completed and ongoing works. As fire safety in buildings continues to be a topic of great focus, we may see even closer scrutiny of such work in light of this ruling.

    Read More

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    3

    Private rental market faces £19bn EPC-upgrade bill

    Private rental market faces £19bn EPC-upgrade bill

    News The cost of getting private rental housing in England up to tougher EPC guidelines by 2025 is set to be around £19bn, new research by Hamptons on behalf of Bloomberg has revealed. The study, which analysed data from the Department for Levelling Up, Housing and Communities, found that almost half of privately rented homes […]

    Read More
    HS2 investigates slurry pool above Costain-Skanska tunnelling

    HS2 investigates slurry pool above Costain-Skanska tunnelling

    News An HS2 tunnel boring machine HS2 is investigating how a roughly 6 square metre pool of bubbling slurry emerged on a rugby pitch in Ruislip, north-west London. The brown foam emerged from the ground on Saturday (18 February), above a site where CSC – a joint venture between Costain, Skanska and Strabag – is […]

    Read More
    Balfour workers vote for March strike action

    Balfour workers vote for March strike action

    News Balfour Beatty workers will carry out three 36-hour strikes on consecutive weekends next month in a dispute over pay. The RMT rail union announced the action following a ballot of Balfour staff working for the Central Rail Systems Alliance (CSRA), a joint venture between the firm, Network Rail, Atkins and TSO. The decision to […]

    Read More